|
|
|
Some
2,500 years ago, architect Eupalinos built a tunnel more than a kilometre
long to supply the Greek city of Samos with water from a spring on the other
side of Mt Kastron. His builders started at both ends and met in the middle.
How Eupalinos managed to avoid creating a big puddle in the mountain remains
a mystery, but somehow the tunnel had the right slope and the water flowed
from one end to the other.
Water does not like to climb. Nor do high-speed
trains, or, for that matter, motor vehicles. Which is why tunnel-building
is undergoing renaissance. As speeds get higher, railways and roads are
getting straighter and flatter - and that means tunnels. Tunnels can wipe
barriers away. For example, when the new railway from Cologne to Frankfurt
is completed in 2002, travellers will be whisked through a few mountains
to their destination in less than an hour, rather than the two-plus hours
it takes now to meander along the Rhine.
But
speed is not the only consideration. Professor Rolf Katzenbach of the
Department of Geotechnology at the Darmstadt University of Technology
offers other benefits. "Some parts of the world are suffocating under
the burden of traffic," he says. "The towns on the Alpine passes between
Switzerland, Austria and Italy are desperate to stop the daily invasion
of heavy goods vehicles. There's only one way to stop it, and that's to
build more tunnels through the mountains." Hence the new Gotthard and
Lötschberg rail tunnels, which will run at base level. For the trains,
the mountains will simply not exist.
Many city streets have also reached their traffic
limit, and going underground is still a solution - hence the construction
of new underground railways in such cities as Brasilia in Brazil and Chelyabinsk
in Russia.
When
Eupalinos built his tunnel, his men hacked their way through solid
rock, which was strong enough to hold up the relatively small structure
that resulted. However, miners and tunnel builders soon learned to hold
their tunnel roofs up in less secure ground with wooden beams and masonry.
A breakthrough came in the 19th century when a British engineer, Marc
Isambard Brunel, developed the idea of protecting the tunnel builders
inside a cylindrical shield as big as the tunnel. The cylinder was pushed
forward as they dug, allowing them to remove the earth as they went. Behind
them, masons built the tunnel walls. The technique was first used in a
tunnel under the Thames, completed in 1843.
That, in principal, is still what happens, but
Brunel would scarcely recognise the machinery that does it now. Huge tunnel
boring machines (TBMs) dig their way through the ground while, directly
behind the protective shield, tunnel rings made of reinforced concrete
segments are fitted into place. A slurry of fine clay particles in water
is used to "lubricate" the drilling process and to carry away the crushed
rock. The slurry is separated from the rock and returned to the process,
while the rock is carried along a conveyor belt to waiting trucks or trains
for disposal.
Such an underground factory is expensive - about
25 million US dollars. It has to be built for each project and precisely
matched to the geology. Specific kinds of cutters and grinders have to
be used for the conditions, as well as specific methods of producing the
pressure differential at the head and of removing rock.
TBMs
are fast.
In good conditions they can build tunnels at a rate in excess of a metre
an hour. They've been used in many of the most dramatic tunnel building
projects of the past few years. The fourth tunnel under the Elbe in Hamburg,
Germany, for example, was driven by the world's largest TBM, which dug
out space for a two-lane highway in one go. But, because of the cost,
such a machine is only worth using for distances of more than two kilometres,
so only one of the 30 tunnels for the new railway between Cologne and
Frankfurt will be built that way. The others will mostly be dug conventionally
and secured using the shotcrete method, with the tunnel being lined with
quick-drying concrete as soon as it is dug.
Water, too, can result in surprises. Brunel's
tunnel had to be abandoned several times because water broke in, and many
of the rocks in which tunnels are built today are saturated with water.
Once it was standard practice simply to pump the water out, but that lowers
the water table, and environmental considerations mean that this is now
seldom done - typically only as a temporary measure while building is
under way.
Usually water is kept out of the drilling process
by the use of excess air pressure matching that of the water, in which
case the workers have to enter the tunnel site through an airlock. TBMs
solve the problem by isolating the drill head from the rest of the machine,
while the tunnel segments seal the tunnel directly behind the shield.
In tunnels driven with the shotcrete method, a concrete lining has to
be added to provide a water seal, as well as to ensure long-term stability
as the shotcrete deteriorates.
But
careful research in advance ensures that the risks are minimised.
Giovanni Barla, professor of rock mechanics at the Technical University
of Turin, says that a project needs to spend 4 to 5 percent of its budget
on preconstruction research if it is to avoid surprises on the way. In
the Gotthard base tunnel, for example, a 5.5-kilometer-long, 5-metre-wide
exploratory adit was driven into the Piora syncline. The research ensured
that a difficult geological area with very high water pressures was avoided.
"Tunnels are getting longer; this means that the kind of geology you meet
is more varied," says Claus Erichsen of Prof. Wittke Consultants for Geotechnical
Engineering in Aachen, Germany. "That calls for new methods."
Katzenbach says that the real development over the past 30 years in tunnel
building has been the understanding that the mountain will hold itself
up. The task of the shotcrete lining or the tunnel rings is just to support
the immediate vicinity. "You only need to support three or so metres of
rock," says Katzenbach, "The mountain itself will bear most of the load."
This understanding has extended to the building
of caverns. Usually in building a cavern, a tunnel is driven first and
then widened out to final size. The roof is secured before the structure
is extended downwards. Barla says, "Once it was usual to build a concrete
arch, but now the securing is done by rock bolting, anchoring and shotcrete."
Caverns are mainly used for storage - Barla was recently involved in the
building of huge kerosene tanks in Israel - although there are also such
buildings as the Gjřvik Ice Cavern, built for the Lillehammer Winter Olympics
in 1994 as an ice hockey rink. Cavern builders have it easier in one respect,
says Barla. "They can often build a cavern in the best rock in the area,
whereas a tunnel usually has to go through whatever is in the way," he
says.
Tunnels
are among the most demanding of major construction projects and, at
up to USD 50,000 per metre of finished tunnel, they're also the most expensive.
But the fascination of overcoming the barriers of rivers, mountains and
seas will ensure that ambitious tunnels will still be designed. The 35-kilometre
Channel Tunnel waited 200 years to be built.
© ITT Flygt AB, Solna, Sweden,
2000. All rights reserved.
|
|